In a surprise move that could benefit PJM Interconnection, four state governors have submitted a joint proposal formulated with the Data Center Coalition (DCC), an industry group, that favors approving connections to data center firms that will generate and add their own power to the grid.
Theย proposalย would offer a fast track approval process for both the data centers and the power sources they would build. The idea was raised last week during a hearing held by PJM, the nationโs largest electrical grid, as it grapples with soaring demands and seeks federal approval later this year to hasten permit reviews.

Pamela Quinlan, a principal atย GQS New Energy Strategies, an energy consulting company that represents the DCC, a leading data center trade group, described the eight-page plan as a โvoluntary and heavily incentivizedโ path for the industry.ย
Quinlan offered limited details during the hearing at PJMโs office near Philadelphia. The proposal generated interest because the four governorsโfrom Pennsylvania, Maryland, New Jersey and Virginiaโhave been critical of PJMโs operations but eager for data center expansion in their states.
The electricity originated by the centersโ power generators would feed into the PJMโs regional grid, bolstering its reliability, according to the proposal. At least one energy researcher who reviewed the proposal said the strategy may also boost reliance by the new data centers on natural gas.
The DCC is an industry trade group for data center operators and cloud providers. Amongย its membersย are the biggest tech companies in the world, including Amazon Web Services, Google, Microsoft and Meta, all of which have invested billions of dollars in developing and deploying artificial intelligence and, in the past couple years, proposing new data centers. AI operations requireย massive amounts of water and power.ย
Jacob Finkel, an aide to Pennsylvania Gov. Josh Shapiro, spoke at the hearing and said he was representing the four states, which are in โstrong alignmentโ with the DCC over the proposal.
PJMโs inability to process grid applications in a timely manner has frustratedย many governorsย across the grid operatorโs 13-state service area. The other states reliant on PJM are Delaware, Illinois, Indiana, Kentucky, Michigan, North Carolina, Ohio, Tennessee, West Virginia and the District of Columbia. It was not clear during the meeting if the other states were consulted by Finkel.
Data centers require around-the-clock electricity and even brief dips can cost millions of dollars in revenue. The fast-track proposal aims to accommodate lucrative investment from tech and financial firms in some pivotal states.
States oversee the siting, permitting and environmental review for commercial projects that require grid access. The states also assess land-use or rights-of-way and construction approvals related to the construction of electric lines and substations.
The DCC-governors proposal essentially relies on the states to expedite permitting and siting for the data operations. Under the proposal outlined by Quinlan, each state can issue directives to expedite projects that will build energy lines or substations. The data centerโs power sources donโt have to be on the data-center site itself. The generators can be elsewhere in the same grid area that is approved by the state.
Under the plan, data centers qualify for the fast lane only if they create power equal to their expected use. For example, a data center site planning to use 50 megawatts must secure or develop 50 megawatts of supply. Those megawatts would be added to PJMโs grid at the time the business is launched.
The proposal includes a measure to combat rising bills for all ratepayers. The proposal would extend or maintain theย current capacity charge set by PJMโwhat customers pay to guarantee power at all timesโfor another year. In July, PJM issued a capacity charge for service from June 2026 to May 2027 that topped 20 percent, and it agreed then to extend the cap to that charge to 2028. PJM said that would mean an increase of aboutย 1.5 to 5 percentย in customersโ bills, depending on their area.ย
The proposal outlined by the DCC would extend the price cap into the summer of 2029.
โSeeing this proposal to extend the price cap for another year is a very significant win for consumers,โ said Abraham Silverman, an energy researcher at Johns Hopkins Universityโs Ralph OโConnor Sustainable Energy Institute. That would shield customers from price spikes as data centers come online, he said.
The DCC and the governors supplied few details about their proposal beyond an eight-page outline. Some analysts said the DCC and the governors need to provide specifics on how each state will review and decide to fast-track the projects.
Paul Sotkiewicz, the president of energy consulting company E-Cubed Policy Associates and a former chief economist for PJM, said states should be wary of how they โshort-circuitโ processes that will affect local residents and governments.
โI can imagine it backfiring on politicians if they do that,โ Sotkiewicz said. โIt all sounds nice on paper, butโฆ.I donโt see how it can happen.โ
โThere are certain processes that they have to follow and procedures that they have to follow to issue permits,โ he said. โThatโs just the way permitting works.โ
Finkel said Pennsylvnia and other states will form a โconsortiumโ to โfigure out how theyโre going to do this.โ Finkel offered Pennsylvaniaโs months-oldย Lightning Planย as an example, which aims for a one-stop deadline-driven framework for power projects permits. The plan, announced in January, would create a new oversight board to coordinate and speed siting and approvals. As of this month, the plan remains a blueprint.ย
Silverman pointed to another concern about the fuel driving the new power sources. States with ambitious climate change goals might have to accept that the data centers that contribute to PJM will be using gas rather than solar or wind power, he said.
โA hyperscale data centerโฆmay be a thousand megawatts. Thatโs a lot of solar,โ Silverman said.
Joseph Bowring, the president ofย Monitoring Analytics, an independent monitoring unit that reports on PJMโs electric power market, said the DCC-governors proposal is missing some notable guarantees.
A central question in the rulemaking discussions over PJM reliability is who should lose power when the grid is stressed, he said. Should data centers lose power first? Should they lose it in sync with everyone? Or should they be the last to lose power?
โThe equitable way to formulate it for these guys who are coming onto the system (and) bringingย 30,000 megawattsย of issues is for them to be interrupted first,โ Bowring said. โIf interruptions were assigned to data centers first,โ he said, it is likely that โdata centers would not sign up for that service.โย
Bowring said even if PJM assigned interruptions โperfectly,โ the fact that there would be interruptions means the grid cannot reliably serve its customer base.
Bowring said the monitoring group advocatesย not allowing data centers to connectย unless the grid can guarantee continual service and reliability.
The plan from DCC and the governors is one of more than a dozen proposals being considered by PJM as it seeks public comment to support a request for a rule changeโknown as the Critical Issue Fast Pathโmeantย to add suppliers to the grid.ย
PJM has also heard its own staff proposal: allowing 10 new proposed projects per year to connect to the grid in as little as 10 months through expedited reviews. Critics said that approach, too, would favor gas-fueled developers.
The federal agency that oversees grid regulations, the Federal Energy Regulatory Commission, will decide whether the change that PJM seeks is lawful and in the public interest. The PJM board plans in December to submit a written request to FERC. There are at leastย three more meetingsย planned by PJM through late November.