LEONARDTOWN — St. Mary’s County sewer and water customers could see two new charges if the General Assembly approves a request from the Metropolitan Commission: a “ready-to-serve” fee on properties that hold a reserved connection but are not hooked up, and a grinder-pump maintenance fee for properties that depend on one. Commissioners reviewed the proposal Tuesday and left the decision to the board that takes office next month.

Nothing is changing yet. The request is one of 14 that county staff brought forward for a first look as the commissioners assemble a package for the county’s legislative delegation, a process the county opened in August. The board is due to decide on Dec. 8 which proposals to carry forward, with a joint meeting with the delegation set for Dec. 15, before the General Assembly convenes Jan. 13.

A county attorney said MetCom sends in a list of changes to Chapter 113 of the public local laws every year, a few dozen revisions that are mostly technical. Two are not. MetCom would rename connection charges as “ready-to-serve” charges to cover properties that have a reserved equivalent dwelling unit, known as an EDU, but no hookup and no immediate plan to connect. MetCom keeps that capacity on its books, and the proposal would codify a modest administrative fee for doing so.

According to the proposal, the estimated impact would be $4.80 per EDU per month for water and $8.92 per EDU per month for sewer. A commissioner noted that owners who have not yet paid the capital contribution fee, which the commissioner put at roughly $18 to $20 a month, already hold capacity at the plant, and asked whether those owners would now pay more. Staff said that is how they understood it, describing the new charge as an administrative cost of keeping the reservation in the system. The Chronicle explained how reserved capacity differs from permission to build in October.

Who pays when a grinder pump fails

The second change drew the pushback. Grinder pumps are the small, property-specific pumps that push sewage to the main line where gravity will not do it. MetCom’s proposal would let it assess a maintenance fee on the properties that benefit, instead of spreading those costs across all customers. Staff said that is the intent, and that MetCom’s actual plans tend to be narrower than the broad enabling language it sends in each year.

One commissioner said he had faced a failed grinder pump on a Tall Timbers property after a line rusted out. By his account, the MetCom director said replacement would run about $40,000 and asked whether he wanted to split the cost. He argued that owners already pay a monthly fee and should not also pay to replace worn equipment, unless something the owner put into the system caused the failure. Another commissioner likened it to buying a warranty and then being told to pay when making a claim.

Staff did not have the answer to that scenario and suggested the commissioners put the question to MetCom’s author of the proposal. The proposal’s page-five explanation covers the grinder-pump fee. As the board closed out the item, one commissioner said the fee looked like another way to charge customers and that it was a matter for the next board.

Other requests heard the same morning included an alternate member for the Alcohol Beverage Board. The commissioners return to the full list Dec. 8, the first regular meeting after the new board is seated Dec. 1.